Botnia Gold (Nasdaq First North: BOTX) announced that a fire broke out on the evening of 10 October in an isolated storage tent at the Fäbodtjärn mine in Sweden. Three specialist vehicles — a concrete truck, a shotcrete machine and a charging vehicle — were destroyed, along with a storage tent of approximately 450 square metres. Two firefighters were hospitalised after smoke exposure; no company or contractor personnel were injured. Production resumed at reduced capacity and is expected to approach full capacity within one week, with full production within approximately three weeks. The company estimated one-off costs at approximately SEK 5–10 million, with no negative revenue impact anticipated for 2026 or likely 2027.